Zone 4 (Winterberry) - Construction Progress - September 18, 2011 (View Gallery)

D+25

  • Concreting of Basement 1 slab, 100% completed.

D+25, D+26, D+27

  • Concreting of Raft slab at Basement 2 completed.
  • Concreting of columns & corewalls from Basement 2 to Basement 1, 100% completed.
  • Concreting of retaining walls at Basement 2, 100% completed.

E24

  • Concreting of slab at Basement 1 completed.
  • Concreting of columns from Basement 1 to Ground Floor, 50% completed.
  • Concreting of retaining wall at Basement 1,  20% completed.

E27

  • Basement 1 Post Tension slab casted.