Zone 3 (Lily) - Construction Progress - September 18, 2011 (View Gallery)

A19

  • Part A : Casting of 4th flr slab completed. Concreting of columns & Core walls from 4th to 5th floors completed.
  • Part B : Casting of 4th flr slab completed. Concreting of columns & Core walls from 4th to 5th floors completed.
  • Concreting of Substation Room with Services completed.
  • Preparation of slab on-grade at Substation in progress. 

A23

  • Part A : Concreting of 4th floor slab completed.
  • Concreting of columns from 4th to 5th slab completed.
  • Part B : Concreting of 6th floor slab completed
  • Columns & corewall from 6th to 7th flr slab completed.
  • Concreting of Substation Room with Services still not started.

D20

  • Concreting of inclined slab with parapet completed.
  • External block work at 1st to 8th  floor in progress, 96% completed

   
D21

  • Concreting of 8th flr slab & mechanical slab completed
  • Block work from 1st to 7th flr completed.
  • Layout of block works at ground flr in progress
  • Concreting of parapet wall 80% completed.

                                   
D22

  • Concreting of 7th floor slab completed.
  • Columns & core wall from 6th to 7th flr completed.
  • Concreting of 7th flr slab completed.