Zone 2 (Rowan) - Construction Progress - September 18, 2011 (View Gallery)

D+16

  • Concreting of slab at Basement 1 completed.
  • Concreting of columns from Basement 1 to Ground Flr, 100% completed.
  • Concreting of retaining walls at Basement 1, 100% completed.

D+17

  • Concreting of slab at Basement 1 completed.
  • Concreting of retaining walls at Basement 1, 100% completed.

E15

  • Concreting of slab at Basement 1 completed.
  • Concreting of columns from Basement 1 to Ground Flr, 100% completed.
  • Concreting of retaining walls at Basement 1, 98% completed. 

E18

  • Concreting of slab at Basement 1 completed.
  • Concreting of columns & core walls from Basement 1 to  Ground Flr,   95% completed.
  • Concreting of retaining walls at Basement 1, 100% completed.